Arcedges Building India LLP · ERPNext Phase 1 · KTree

Job Status — header level

One job at a glance: what is blocked (holds first, with age, quantity and money stuck), what has passed (gates with dates), what to watch, and how far every stage has gone — % measured in MT.

⚠ sample data — design mockup for review, not live figures

Status view — J465

Header level: what is blocked, what has passed, and how far every stage has gone.

J465 · Voltsun Labs Pvt Ltd · Cell Building · Naidupeta AP
520 MT · ₹5.2 Cr · zero date 04-Jul · day 53 · B1 · PH-1…PH-4
✗ HOLD · payment before dispatch — PH-2 milestone unpaid · 4 days · 96 MT ready & waiting · ₹96 L blocked
release: management waiver · gate G1 · raised 22-Aug by PMC
⌛ WAIT · erection readiness PH-2 — 46% of phase material on site, threshold 50–60%
clears automatically as PH-2 dispatches land and pass MVR
GATES PASSED ✓ advance 12-Jul ✓ colour conf. 15-Jul ✓ GAD approved · 12d ✓ BOM released 97% ✓ PPC sync ✓ G2–G6 last truck ✓ weight 198/520 within ±3%
WATCH ⚠ PBG expires 30-Sep · 35 days ⚠ 3 MRS open at site 1 change order · +6 MT · approved TPI job · inspector resident
Drawings
100% · ABD ✓ · GAD ✓ · shop 100%
Procurement
100% · 42/42 POs received
Production
62% · 322/520 MT · 396/638 pcs
Dispatch
38% · 198 MT · 11 trucks
Site / MVR
35% · 186/198 MT verified · 2 short-receipts
Erection
12% · 62 MT client-inspected
Billing
31% · ₹1.62 / 5.2 Cr